A14.2 Development methodologies

Software development, law and ethics · A level · OCR H446 1.2.3, AQA 7517 4.13.1.1, Eduqas A500QS 1.5 · about 45 min

BugBotLab

What this lesson is about

Waterfall, spiral, agile, extreme programming and rapid application development: how each works, when to use it, and planning agile sprints.

Questions 6 marks in all

  1. [1 mark]Which methodology is driven by identifying and reducing risk on each loop, often by building prototypes?

    1. AThe spiral model
    2. BWaterfall
    3. CExtreme programming
    4. DRapid application development
    Answer: A. Boehm's spiral model goes round objectives, risk analysis, development and planning, with the biggest risks dealt with first.
  2. [1 mark]A hospital commissions software to control drug doses. The requirements are fixed by regulations and must be fully documented. Which methodology suits best?

    1. AWaterfall
    2. BExtreme programming
    3. CRapid application development
    4. DAgile with two-week sprints
    Answer: A. Stable, fully specified, safety-critical requirements suit waterfall's sign-off at each stage and heavy documentation.
  3. [1 mark]Which of these are practices of extreme programming?

    Tick every answer that is true.

    1. APair programming
    2. BTest-driven development
    3. CContinuous integration
    4. DSigning off each stage before the next begins
    5. EHeavy upfront documentation
    Answer: A, B, C. XP uses pairing, tests written before code, frequent integration and releases; sign-off and heavy documentation belong to waterfall.
  4. [1 mark]What is a drawback of rapid application development?

    1. APrototypes built quickly can lead to poorly structured, inefficient code
    2. BThe users never see the system until it is finished
    3. CIt cannot use prototypes
    4. DRequirements must be fixed before any work starts
    Answer: A. RAD's speed and time-boxing trade against code quality, and it needs a lot of the users' time.
  5. [1 mark]In agile, what name is given to the number of story points a team completes in one iteration?

    Answer: velocity. Velocity is used to plan how many stories fit in each future sprint.
  6. [1 mark]Why does waterfall cope badly with changing requirements?

    1. AA change found late means going back through stages that were already completed and signed off
    2. BIt does not have a testing stage
    3. CThe client is involved in every iteration
    4. DIt uses pair programming
    Answer: A. Each stage builds on the signed-off output of the one before, so a late change is expensive to make.

The task: plan the sprints

Plan the delivery robot's sprints. VELOCITY is the whole number of story points the team finishes in one sprint. backlog is a list of (story, points) tuples in priority order: story is a string, and points is a whole number of 1 or more. 1. Go through the backlog in order. Any story with more points than VELOCITY cannot fit in a sprint: print too big, split it: <story> and leave it out of the plan. 2. Put the remaining stories into sprints, in order. Add each story to the current sprint while the sprint's total stays at or below VELOCITY. When the next story would take the total over VELOCITY, that sprint is finished and the story starts a new sprint. 3. Print each sprint as sprint <n>: <stories> (<total> points), numbering from 1, with the stories separated by , . 4. Finally print sprints needed: <n>. Compare with VELOCITY in your code, not the number 8. The robot stays still.

# the two lines every program starts with: the commands, then the robot
from bugbot import *
connect()

VELOCITY = 8
backlog = [("drive to a bay", 5), ("stop at the wall", 3), ("beep when blocked", 2), ("map the room", 13),
           ("report battery", 1), ("follow a line", 8), ("avoid people", 5), ("log each delivery", 3)]

The hint students can ask for: Deal with the stories that are bigger than a whole sprint first. Then keep a list of the stories in the sprint you are filling and its running total; when the next story would take the total past the velocity, print that sprint and start a new one with the story. Remember to print the last sprint after the loop.

A solution

# the two lines every program starts with: the commands, then the robot
from bugbot import *
connect()

VELOCITY = 8
backlog = [("drive to a bay", 5), ("stop at the wall", 3), ("beep when blocked", 2), ("map the room", 13),
           ("report battery", 1), ("follow a line", 8), ("avoid people", 5), ("log each delivery", 3)]

ready = []
for story, points in backlog:
    if points > VELOCITY:
        print("too big, split it:", story)
    else:
        ready.append((story, points))

sprints = []
current, total = [], 0
for story, points in ready:
    if total + points > VELOCITY:
        sprints.append((current, total))
        current, total = [], 0
    current.append(story)
    total += points
if current:
    sprints.append((current, total))

for n, (stories, total) in enumerate(sprints, start=1):
    print(f"sprint {n}: {', '.join(stories)} ({total} points)")
print("sprints needed:", len(sprints))

Any program that meets the task's checks is marked correct in the simulator; this is one way, not the only way.